Stories you can’t estimate yet: what to do instead of guessing
Published November 11, 2026, updated November 18, 2026
Every deck has a ? card, and it’s the most honest card in it. It means “I can’t size this yet”. When several people play it, or the votes spread from 1 to 13, the team doesn’t have an estimation problem. It has a story that isn’t ready. Voting harder won’t fix that, and a number agreed in that state measures the unknown, not the work.
Here’s what I’ve seen cause it, what we did about it, and the process we ended up with.
Two reasons a story can’t be sized
In my experience it usually comes down to one of two things:
- The requirements aren’t there. They’re missing, or they contradict each other, so different people are effectively estimating different stories.
- There’s a technical problem. Someone finds a technical problem that makes the planned solution unreasonable.
In the room, both can look the same: a split vote and a discussion that goes in circles. They need different fixes, so it’s worth naming which one you have before doing anything else.
When the requirements are the problem
We took the story to an extra grooming session with the product manager and the stakeholders, to get the missing answers and settle which of the conflicting requirements wins. Estimating it waited until then.
When the technical side is the problem
We explained the problem to the product manager in plain terms and offered alternative solutions to choose from. That turns a dead end into a decision, and it puts the decision with the person who owns the priorities.
Often we couldn’t offer good alternatives straight away. Then we needed an extra investigation first, to collect data about the problem and come back with more precise options. That investigation is what many teams call a spike.
The process we ended up with
Sorting this out in the planning meeting wastes everyone’s time, so we moved it earlier and made it visible:
- Pre-grooming. Before planning, the stories are read through so the open questions surface before the meeting, not during it.
- A label for the product manager. A story with open questions is set aside and marked with a dedicated Jira label, so the product manager sees it and answers the questions in the comments.
- A separate task for the investigation. If the story needs technical investigation, or more work with the product manager and stakeholders, that becomes its own task, limited to a day at most.
- The story itself waits. It’s marked as blocked and left out of the sprint’s scope. Usually it goes into the next sprint, once the investigation is done and it can be estimated properly.
The time limit matters. Without it, an investigation easily turns into a project of its own, and the blocked story waits on it indefinitely.
Why not just estimate it high?
It’s tempting to vote a 13 on anything uncertain and move on. The trouble is that the 13 then sits in the sprint, looking like a plan. If the answers come back simple, the sprint carries padding it didn’t need. If they come back hard, a 13 wasn’t enough either, and the sprint slips. I’ve seen the second case on real projects: requirements that weren’t investigated enough moved a deadline. The velocity forecasting guide shows what scope that grows mid-project does to a forecast.
Big uncertain stories also make sprints unpredictable for a plainer reason. The story size simulation shows how much one large story can swing a sprint, even when it was estimated well.
In the room
On this site the ? card is left out of the average, so a round with two question marks still shows a number. Don’t take it. If more than one person plays ?, stop and find out what’s missing, as the guide to split votes suggests. Put the story aside, write the open question where the product manager will see it, and move on to the next story while there’s still energy in the room.
Want to try this with your team? Start a free room. No sign-up, and the link is all your team needs.