Why splitting stories makes sprints predictable: a simulation
Published November 11, 2026
“Split that story” usually comes with one reason: big stories are hard to estimate. That’s true, but there’s a second reason that holds even when every story is estimated equally well. Big stories make the sprint lumpy. A team that gets halfway through a 21-point story has nothing to show for it this sprint, and 21 extra points in the next one.
That lumpiness is easy to wave away in a planning meeting and hard to ignore in a velocity chart. A simulation shows how much of it comes from story size alone.
The model
A team gets through about 40 points of real work a sprint, give or take 10% for holidays, support duty and meetings. It works through an endless backlog of stories that are all the same size, one after another. Each story’s real size misses its estimate by about 22% in a typical case, which is the error of a five-person vote in the planning poker simulation. A story still in progress when the sprint ends carries over. Velocity is the points of the stories finished in the sprint, and each story size gets 200,000 sprints.
Same average, very different sprints
| Story size | Average velocity | Low sprint | High sprint | Sprints under 30 points |
|---|---|---|---|---|
| 1 | 38.1 | 33 | 44 | 1.8% |
| 2 | 38.0 | 32 | 44 | 2.5% |
| 3 | 38.1 | 30 | 45 | 2.9% |
| 5 | 38.1 | 30 | 45 | 3.9% |
| 8 | 38.1 | 32 | 48 | 8.3% |
| 13 | 38.1 | 26 | 52 | 27.6% |
| 21 | 38.0 | 21 | 63 | 29.6% |
The average doesn’t move. It stays at about 38 points a sprint whatever the size, because unfinished work isn’t lost, just late. What changes is the spread. With stories of 1 to 5 points, eight sprints in ten land between 30 and 45 points. With 13-point stories the range is 26 to 52, and with 21-point stories it runs from 21 to 63.
Sprints that deliver under 30 points stay below 4% up to 5-point stories. They reach 8.3% at 8 and 27.6% at 13. That jump is the useful part. Below it, a sprint’s ups and downs average out over many small finishes. Above it, one story landing a day early or late decides whether the sprint looks fine or terrible, and nothing about the team has changed.
Why that matters for forecasts
A release date worked out from velocity is only as steady as velocity. With 21-point stories, the range that holds eight sprints in ten is 42 points wide, nearly four times the 11 points of 1-point stories. A forecast has to carry that width, or it will be wrong often enough that nobody trusts it. The velocity forecasting guide shows how to turn a range of past sprints into a range of dates.
Commitments hold less often
The second chart asks a planning question. Commit to 32 points, 80% of the average capacity, and how often does the team finish all of it?
| Story size | Stories | Commitment met |
|---|---|---|
| 1 | 32 | 92.8% |
| 2 | 16 | 90.4% |
| 4 | 8 | 87.1% |
| 8 | 4 | 82.4% |
| 16 | 2 | 77.9% |
| 32 | 1 | 74.1% |
In 1-point stories, the commitment holds in 92.8% of sprints. As four 8-point stories it holds in 82.4%, and as one 32-point story in 74.1%. The amount of work is the same each time. Only the size of the lumps changes, and bigger lumps leave less room for one of them to run long.
Does it depend on the error size?
Not in shape. The script also runs every story size with a smaller error and a larger one. The ranges move, but small stories stay steady and big ones swing: 1-point stories stayed between 29 and 45 points at both settings, while 21-point stories ranged from 21 to 42 with the smaller error and from 21 to 63 with the larger one.
What to do with this
- Split anything bigger than about a fifth of your velocity. For this team, at 40 points a sprint, that means anything above 8, which is where the bad sprints start piling up. A faster team can carry a 13; a slower one should split earlier.
- Keep the big ones out of the sprint backlog. Leave them as T-shirt sizes on the roadmap until someone has broken them down.
- Read a bad sprint in context. With big stories in play, one low sprint says little about the team. Look at several before drawing conclusions.
- Once stories are consistently small, consider counting them. When every story is a 1, 2 or 3, the points add little. Counting stories is one of the alternatives worth trying.
What the model leaves out
The team works on one story at a time, where real teams run several at once and finish them at different points in the sprint. Every story here is estimated equally well relative to its size, but big stories are usually estimated worse, which would make the swings larger still. Splitting isn’t free either: each piece needs its own review, testing and a bit of coordination. And the 10% sprint-to-sprint variation in capacity is an assumption.
Change any of those and the percentages move. The script is short, runs in a few seconds with Node.js, and has the settings at the top.