Planning poker is easy with five people. It gets harder with eight, and with several teams in one session it can fall apart. I’ve planned in groups of 5 to 20 people, often across teams, and a few habits held up.

Everyone on the team votes

On my teams, everyone voted on every story, not only the people expected to build it. A tester or a front-end developer often sees something the person assigned to the story doesn’t, and voting is how they get asked. It’s also how knowledge spreads: a team where only the assignee looks at a story ends up with one person who understands it.

There was one exception. Some stories belonged to a very specific project, or one person had already investigated them and nobody else had the context. Then there were two options:

  • Ask that person to walk everyone through it, so the rest of the team can vote with some understanding.
  • Let that person estimate it alone, but only if the story isn’t critical. If a wrong number would hurt, it’s worth the few minutes of explanation.

How fast it can go

A team of eight can work through about 20 stories in an hour and still look at each one properly. That’s three minutes a story, which matches the two to three minutes the facilitator’s script suggests. It only works when the stories are ready: described, understood, and small enough to size. A story with an open question breaks that pace, and it shouldn’t be voted on yet.

Several teams in one session: split up

When several teams planned together, up to 20 people, we didn’t vote as one big group. We split by team, and each team estimated its own stories. If you do the same, keep the joint part of the session for what really is shared, such as priorities and dependencies between teams.

That fits what the planning poker simulation found. Going from one voter to five takes most of the error out of an estimate, and going beyond that adds little accuracy but many more split votes to talk through. Twenty voters on one story mostly buys you a longer meeting. Splitting by team keeps each vote to the people who know the work.

What breaks first: attention

In long sessions, the thing that broke was attention. People started playing middle-of-the-road cards without really engaging with the story, a vote that looks like an opinion and isn’t one. I think it was mostly tiredness from long planning sessions.

What helped was asking. Leading questions about the story, and asking people why they’d picked their particular card, brought them back. Sometimes we had to vote again after that.

A few things make that less likely in the first place:

  • Keep the session short. If 20 stories take an hour, 60 stories don’t belong in one sitting.
  • Take the break when someone asks for it. That’s what the coffee card is for.
  • Watch for a run of identical middle cards. Agreement on the first vote is rarer than it feels, as the simulation shows, so a long streak of it is worth a question.
  • Use a timer. In a room here, the auto-reveal timer starts with the first vote and turns the cards over when it runs out, which keeps the pace without anyone having to nag.

The practical side online

A room on this site holds 50 connections, so even a joint session fits. When you split by team, give each team its own room and its own link. People who need to follow a team’s estimates without voting, such as a manager or someone from another team, can join as spectators. They see the results but aren’t counted in the average, and the round doesn’t wait for them. If anyone is on a weak connection, the remote guide has what to do about it.