Is planning poker still worth it? What happened when we skipped it
Published November 11, 2026
Every team that has played planning poker for a while asks the same question: is this meeting worth an hour of everyone’s time? Some teams decide it isn’t and stop estimating altogether. Others keep the estimates but look for a cheaper way to get them.
I’ve seen two cheaper ways tried, and both made things worse. I’ve also seen a way of skipping the vote that works. All three are below, followed by what they suggest about the question itself.
Letting whoever does the task estimate it
On one team, estimates were handed to the developer who would do the task. Nobody else voted. Two things followed. The estimates went up, because people put more buffer into them. And knowledge sharing got worse: with only one person looking at each story, nobody else learned how it worked.
We never stopped estimating, though. The estimates mattered for planning delivery dates, so they were kept the whole time. What disappeared was the second opinion, and with it the conversation that a split vote starts. The split is often where a team finds the missing requirement or the forgotten migration.
Voting in the chat instead of with cards
Another time, the tool was replaced by votes typed into the meeting chat or into Slack. It worked worse. The votes arrived one at a time, so everyone could see the earlier ones, and people who weren’t sure changed their number to fit what was already there.
That’s anchoring, and it’s the reason the cards are hidden in the first place. The anchoring guide puts numbers on what it costs. In a simulation, a team where everyone leans halfway toward the first number agrees far more often and estimates worse, and the one person who knows about a problem rarely gets to say so. A chat thread is a machine for producing that first number.
Skipping the vote, but only for some stories
What did work was not voting on everything. Very small tasks got the smallest estimate straight away. Tasks that kept coming back, the same kind of change done many times before, got the number they’d had before. We skipped the round for those, with one rule said out loud: anyone who disagreed could object and explain why.
That rule matters. Without it, skipping the vote quietly turns into one person deciding. With it, the team keeps the second opinion for the stories that need one and saves the time on the ones that don’t.
So is it worth it?
In each of these cases, the cards themselves weren’t the problem. The estimates got worse when the team lost what the cards protect: a first estimate made before hearing anyone else’s, and several people looking at the same story. Keep those two and the method is doing its job, whatever you call it and however you run it.
If the meeting feels too long, there are better fixes than dropping the vote:
- Skip the routine stories, as above, with the right to object.
- Keep a reference list so nobody argues from scratch. Choosing a baseline story takes about half an hour.
- Split big stories before the meeting. They take the longest to discuss and, as the story size simulation shows, make velocity swing.
- Time-box each story. Two to three minutes is enough for a story that’s ready. The facilitator’s script shows how.
And if your team really doesn’t need estimates, because nothing depends on a date, that’s a legitimate choice too. The alternatives guide covers counting stories instead of pointing them.